<< Click to Display Table of Contents >>

Set Date Option


Sets the options for the gantt chart. Click Next button, after setting fields.

Indent

Use Indent - Sets whether to use indentation.

Field that indicate critical dates

Sets the field to indicate critical date.

Plan/Result Type

Defines the method to show the plan and actual results.

Start Date, End Date

Sets the entire period to draw a Gantt chart.

Auto

Sets date automatically according to the data value.

Parameter

Sets Start/End Dates as ODI parameters in ODI currently used. Note that ODI parameter for Start/End dates should be named gt_fromDate/gt_toDate).

FormParameter

Sets Start/End Dates as Form parameters in ODI currently used. Note that Form parameter for Start/End dates should be named gt_fromDate/gt_toDate.

Setting

Sets Start/End Dates inserted through Wizard.


Example - Plan/Result Type

If you select Horizontal

If you select Vertical